Loading...
 

eddiesplace

My place.

Stuff from 2016

2017

Sept.

22nd - Lock up.

Locked Red
Apart from two pieces of trim the AGS builders have finished.
Next the tanks are going to be installed by different people.
I moved the fourth trailer load of stuff down - it has hardly made a dent in what I have remaining.
It has felt weird leaving the place with doors and walls missing. It now feels weird locking up.
Because the screens can be latched from the inside but have no key locks it is possible to lock yourself out when exiting via the garage.
The glass door latches are different to anything I've used before and took a few minutes to work out for the first time - no instructions.

August

22nd

Stacker Red
Slow progress. The builders are moving between three different jobs.
I let them know wet weather was forecast and they made the upper level water resistant. All windows are in along with the deck "stacker" door. Some sheeting is missing but it is sealed well enough rain should not be able to wet the mezzanine particle board underfloor. I don't think it would withstand a storm. Storm session starts about now but no storms are expected in the next week or two. It should be storm proof soon.
It would also be good to get the guttering and tanks in place to capture some rainwater.

July


12th


Roofandrock2
Mostroofon Barn Ceiling

1st

The crane is onsite - delivered on a Saturday. Looking promising for Monday.
The wet has repeatedly delayed work. Another company doing work at the southern end of the co-op have been delayed even longer.
Theirs is a smaller job but access to the South is far worse than to my site.
Last week Glen did 1.25 hrs work repairing my road with his excavator. We are coming to the end of the heavy traffic.
In the meantime I'm repairing water-damaged shelves in readiness for moving them to the new place.

I did move my para-glider onto the property (not on my site) and got bogged for the first time in about 20 years.
It has been wet wet wet with no time to dry out between rain periods.

June

16th

Wet wet wet.
The frame kit has been on site for 3 weeks but no construction. The bridge has been underwater four times since Saturday.
Windows are due from next Tuesday but it is extremely unlikely AGS will be ready.
There was another stuff up. After many reminders that I didn't want concrete under the deck and assurance the plans would be corrected they poured a slab under the deck area. Unless you are there to supervise there are almost always screw-ups. I'm glad they don't build aircraft.
One stuff up on my part is I assumed the roof support would be like all the sheds I've seen for the last 10 years - un-trussed with a strong top bracket.
My mistake - it is trussed and this impacts the look I was after. Slightly moving a wall and making the trusses a feature might work.

I was going to move my para-gilder on the property today but the weather wasn't good. Maybe next week.

I've used the wait to work on my node-red IOT system for remote monitoring of the building. Getting a remote connection over mobile (4G) network is not trivial. I finally succeeded by using a pagekite.me (pagekite.net) account.

May

15th.

My three Aluminum ground floor doors were left off the G.James order so I've sorted that out. I was surprised that my Aluminum windows and doors have wooden reveals. I was trying to avoid wood near the ground floor perimeter. In particular the bottom of the doors are quite close to termite bearing soil. Two or more doors are likely to open onto garden beds which are termite friendly.
I upgrade all the reveals to H3 treated pine.
I was not shocked by the window bill but was by the price of the doors. In particular the garage doors.
I want to be able to insulate the garage doors or have them pre-insulted. Tilt and panel-tilt are about $2k a piece without insulation.
Insulated panel-tilt $2800 each.

8th.


4th.

The cement pour was planned for tomorrow but has been delayed till Monday because of wet weather.
To kill time I've done some more work on the sketchup model.

Over the last 3 months I've also been working on the "smarthouse" electronics and software.
I have a small node-red network running.
I've also ordered bits and pieces such as water pumps and pressure gauges.

1st.

Site prep starts.

April.

18th.
This week is expected to be a little damp.
Work scheduled to start on or about the 24th.

March.

30th.

Site flood testing in progress. Flood levels are approaching the 1954 record.
Creek height at Nimbin almost 8 metres and rising.
8.7M....Peaked at 8.7.... for now.

27th.

Too wet to start, tropical cyclone Debbie probably isn't helping.
ATM I'm not optimistic we will have good weather till after Easter but perhaps the forecasts will improve once Debbie blows out.

20th.

One week to planned start. I did yet another rough peg out.
Pad looks good for planting rice ATM.
Our bridge was under 5M of water last week with minor bridge damage.
We were flooding in briefly after I took this photo.
Current forecast is for showers on the 27th and fine for the 28th.
Fingers crossed for a start next week.
Site13 Paddy

15th

Wet weather.
Site prep planned for the 27th if the weather Gods start to behave.

1st.

Nothing happened in February.
Today I heard I have approval and work is expected to start in a few weeks as long as the weather co-operates.

January.

19th.

Housepad2

Another round of council approvals is in progress. AGS submitted the last lot of information on Monday and we have no idea when we will get a response - it could take months (PS it did take almost 2 months).
We only have one impossible condition left. LCC approved our effluent plan but amended it with a clearance which isn't physically possible.
My drainage engineer is waiting for LCC to return his call.
I met with AGS on Tuesday and most of the loose ends are under control - for now.
One roller door position is still uncertain and I need to choose the trimming colour - possibly
"paperbark".
We ordered the two main 27500L water tanks - a bit over $3000 each - pale eucalyptus colour like the house walls.
Back to - wait wait wait.


eddie

Created by eddie. Last Modification: Saturday 23 of September, 2017 02:38:20 EDT by eddie.

Last-Visited Pages

Last wiki comments

No records to display

Online Users

12 online users

Shoutbox

admin, 08:08 EDT, Mon 01 of Aug, 2016: upgrade to tiki-15 Formatting broken.
admin, 02:33 EDT, Wed 30 of Sep, 2015: Website moved to Binarylane in Brisbane.
admin, 07:27 EDT, Tue 14 of Aug, 2012: Upgrade to tiki-9. A few thousand bogus accounts have been deleted. The rest should be gone tomorrow. Registration has been turned off and 800 odd spam comments removed.
eddie, 06:14 EDT, Wed 11 of Apr, 2012: upgraded to 8.3
admin, 03:19 EDT, Sun 17 of Apr, 2011: comments are now moderated. If spam continues new registrations will be stopped.